Real Case Study

Twin Workshop Units: Refurbishment EPC Modelling Near Exeter

How we used SBEM modelling to guide the refurbishment of two adjacent industrial workshop units, achieving Band C with a clear pathway to Band B through targeted insulation and efficient heating systems.

185.7 sq m per unitNear Exeter, DevonWorkshop & OfficesRefurbishment Project

Project Overview

Energy Performance Direct was instructed to carry out SBEM modelling for two adjacent industrial workshop units near Exeter undergoing refurbishment. Each unit comprises approximately 185.7 square metres of useful floor area, with ground floor workshop space and first floor office accommodation.

The client required draft EPCs modelling the intended improvements to confirm the achievable ratings before committing to the refurbishment specification. This is a practical and cost-effective approach: by running the SBEM calculations in advance, the client could confirm that the proposed works would achieve their target rating and identify any additional measures needed to reach a higher band.

Although the two units are structurally very similar, their differing orientations mean solar gains affect each building differently, producing slightly different EPC ratings despite near-identical specifications. This is a common occurrence with adjacent industrial units and demonstrates why each building requires its own individual assessment.

Rating Comparison

First Unit

D72

Baseline

C72

After Refurb

B41

With Additional Measures

Second Unit

D72

Baseline

C68

After Refurb

B38

With Additional Measures

The 4-point difference between units is caused by orientation and solar impact. This demonstrates why each building requires individual SBEM assessment even when construction is identical.

185.7

Floor Area (sq m each)

24.44

kgCO2/m2/yr BER

261.16

kWh/m2/yr Primary

Refurbishment Specification Modelled

The client provided their intended refurbishment specification, which we entered into the SBEM model to calculate the achievable ratings. The following improvements were modelled as the baseline refurbishment package:

LED Lighting Throughout

  • LED light panels at 100 lumens per circuit watt with a Light Output Ratio (LOR) of 1
  • LED bulbs to WC areas with automatic on-off controls

Heating and Cooling

  • First floor offices: AC units with minimum COP of 3.5 and SEER of 3.5 with local time and temperature controls
  • Ground floor workshop: unheated (no fixed heating)
  • Electric heaters with time and temperature controls to WCs and stairwells

Building Modifications

  • Front large windows replaced with vehicle access door
  • Ground floor workshop and first floor office layout retained

Existing Constraints

  • Uninsulated ground floor external wall cavities
  • Uninsulated metal frame walls on first floor
  • Uninsulated ground floor, exposed floor and roof

The Path from C to B

With the baseline refurbishment achieving Band C, the client asked what additional measures would bring both units to Band B. Our SBEM modelling identified two straightforward improvements that together deliver the step-change needed.

Priority MeasuresC to B
  • Insulate above the first floor suspended ceiling

    Achieve a U-value of 0.42 W/m2K. This requires approximately 100mm of mineral wool insulation above the suspended ceiling, a relatively low-cost measure that delivers significant improvement in the SBEM model.

  • Add weather compensation controls to the new AC units

    Weather compensation adjusts heating output based on external temperature, reducing energy consumption. This is often a low-cost addition when specifying new AC systems and delivers meaningful benefit in the SBEM calculation.

These two measures alone bring the first unit to B41 and the second unit to B38.

Additional MeasuresTowards Band A
  • Insulate the external walls (cavity fill and/or external insulation to metal frame sections)
  • Replace existing windows with double or triple glazing
  • Insulate the exposed floor
  • Insulate the ground floor
  • Add as much insulation as possible to the roof space
  • Install solar PV panels on the roof

Each of these measures would further improve the rating. Combining several would push towards Band A.

Baseline EPC Recommendations

The baseline EPC assessment identified several long-payback recommendations. While none offered short or medium-term payback on their own, their combined impact is significant when pursuing higher ratings:

Introduce cavity wall insulation to uninsulated external wall cavities

Medium Impact

Install secondary glazing or replace high U-value windows

Medium Impact

Add weather compensation controls to heating system

Medium Impact

Install or improve loft insulation in poorly insulated roof spaces

Medium Impact

Consider installing solar water heating

Low Impact

Key Takeaways

Pre-refurbishment SBEM modelling allows clients to confirm achievable EPC ratings before committing to a specification, avoiding costly mistakes and ensuring the desired band is reached.

Identical buildings can achieve different EPC ratings due to orientation and solar impact. Each unit requires its own individual SBEM assessment even when construction specifications are the same.

Efficient LED lighting with high luminous efficacy (100 lmn/W) and proper controls contributes significantly to achieving good ratings in workshop and office environments.

The step from Band C to Band B can often be achieved through relatively modest additional measures such as ceiling insulation and weather compensation controls, without major structural changes.

AC systems with a COP of 3.5 or better, combined with local time and temperature controls, are highly effective for first floor office spaces above unheated workshop areas.

This advice is impartial and independent of any installers or specific products. We always recommend obtaining 3 to 5 like-for-like quotes to get an accurate idea of installation costs.

Planning a Refurbishment? Get Your EPC Modelled First

Our accredited assessors can model your intended improvements before work begins, confirming achievable ratings and identifying the most cost-effective route to your target band.